|
|
|
NRF
Development
Images
Created
7/3/26
|
|
|
|
 |
|
|
Construction of Ryan II:
The Initial Concept
Below are some of the images that NU released in September 2022 of the
planned stadium. Since then, the school has modified the design a bit.

The new stadium, with its huge overhang and multiple tiers.
The south endzone appears to have a no-seat snake pit of Wildcat partying.

Note on the left side of the drawing that Welsh-Ryan stands alone. The new stadium is on the same site as the old, but
rotated about 25 degrees. The exterior's design has since changed somewhat since this rendering..

Upgraded sight lines and disabled access. However, same hot dogs.
Also, take that Wisconsin! Touchdown!

The beautiful new facility's campus will be perfect for kite flying,
even on the calmest day. The magic of the enchanted lakefront!

Ice skating returns! The old Dyche stadium had a nearby rink in the 1960s and '70s;
it appears the new stadium could have one as well.
Construction of Ryan II:
The Foundation
The
first step in Ryan II's construction was preparation of the site and
the stadium's foundation. This was a massive undertaking.
This
photo was taken in July 2024, as the foundation was being dug. To give
some perspective on how big this footprint is, the blue fence in the
background is next to Ashland Avenue.
The area
cordoned off in yellow is the "donut," the footprint for the playing
field. That area's surface was dug even further down. After this dig,
crews installed an elaborate draining system at the donut-- it is
needed, given how far under the surface the new playing field is. Most
of the front tier seats are underground, and the playing surfface will
be 26 feet under street level. This is a huge step from the old Ryan
Field's five feet beneath the previous Dyche Stadium field.
An
amazing illustration of the system of caissons and anchors required for
the stadium's foundation; some of the anchors are embedded over 80 feet down.
This view is facing the eastern side. Note the large underground
structure in the foreground that will serve as a below-ground loading
dock (and other functions) for the new stadium.
A cut-away of
the stadium with its caissons and anchors. The red line shows roughly
where street level will be and just how far underground the playing
field will sit.
The playing field will be turf, and-- unlike fields at Michigan State
and elsewhere that use a concrete pad under the turf-- NU is installing
a granular pad under the turf, allowing flexibility and more "crowning"
of the field. Again, this is to help with drainage.
A last view of
the site as it was in July 2024. You can clearly see the foundation retaining wall and the
donut, giving a sense of the scale of the work.
Construction of Ryan II:
The Framework
This photo,
posted by NU Athletics Chief Revenue Officer Jesse Marks, shows the
interior of the stadium on May 30, 2025. The foundation is done, the
lower bowl nears completion, and the framework for the upper tiers is
under construction.
An exterior view from Ashland, May 31, 2025.

Exterior view of where the northwest tower had stood, May 31, 2025.
Overhead shot from CBS 2 Chicago (June 2, 2025) shows the progress with the interior bowl.
Construction of Ryan II:
The Structure

August 28, 2025: The canopy is lifted into place. [WLS TV]
By early September 2025 the final sections of the roof had been placed. [NU video]
Sunset, October 24, 2025. [Jesse Marks]
By late October 2025, the structure was nearing completion. [Primo Media]
May 6, 2026: Seating tiers are being installed, and the playing surface foundation is done. [Adam Rittenberg]
May 27, 2026: Pat Ryan Jr. points out construction details to incoming NU president Mung Chiang. [NU photo]
June 24, 2026: Work continues on the seating tiers, and workers begin installing the FieldTurf. [NU Photo]
June
30, 2026: Just one week later, the field is installed. Work is wrapping
up on the Purple Wall, the students' standing section. [Chicago Tribune]
Construction of Ryan II:
The Final Stages
Coming soon.
|
|
|